Keller, world’s leader in geotechnical solutions, announces the completion of its first interlocking pipe pile (O-pile) system for Alamos Island Gold Mine in Dubreuilville, Ontario.
When the Gold Mine encountered unexpected ground conditions at the proposed site for their tailings dam expansion, a 40m (131 ft) long cut-off wall was required.
Various solutions were considered but with several meters of thick sand and gravel till, cobbles, boulders underlaid by bedrock, and flowing water conditions, O-piles were chosen as the preferred solution.
Other benefits of using O-piles include rapid construction using a rotary percussive drilling process in a single pass and a watertight seal using mechanical interlocks. Like sheet piles, the O-pile system creates a cut-off wall and can be used for excavation support. However, while sheet piles would refuse to drive through rock and boulders, a down-the-hole hammer is used to advance the O-pile through these conditions.
Keller crews installed 68 O-piles with lengths varying from 5m (16.4 ft) to 11m (36.08 ft) as required. O-piles were 610mm (2 ft) in diameter. Project Manager Anojan Siva states, “We were involved early on in the process to explain the pros and cons of several potential cut-off wall techniques.” He continues, “We were able to discuss and resolve anticipated constructability challenges, technical considerations, and address the time-sensitive requirements for this critical project."
Overall, Ledcor and Alamos Gold, the client and owner respectively, were extremely pleased with the team’s professionalism and resourcefulness, and execution of the cut-off wall. During construction, Keller provided high caliber experienced personnel working six days a week for six weeks. “We were able to provide a high-quality solution using a pile guide/template to ensure pile location and verticality; and performed continuous inspection and monitoring of all activities,” Anojan said. The project was completed on schedule and Keller has already planned future projects using O-pile technology.
For more information on O-pile services offered by Keller, contact Business Development Manager Dan Maclean by phone at 519-853-3216 or by email.
Source: Keller Announcement
Keller will participate in a Miami project in which, for the first time in 50 years, auger cast pil...
Keller North America provided slope stabilization and deep foundations solutions for culvert constr...
Keller installs auger cast piles for the first FDOT project in over half a century, supporting a ne...
Keller Poland has completed its first marine combi-wall project in Gdansk Port, Poland, helping wit...
Keller UK handled the design and construction of the 141 Harley Street project in London, UK. Kel...
The Regional Municipality of Wood Buffalo has a long history of overland flooding since 1835, with...
As a previous mine pit and tailings pond, the Base Mine Lake has residual bitumen forming two mats...