A new milestone was reached after the completion of the 320-metre Westbury Viaduct in the construction of HS2 which is located at the UK’s high-speed railway. Specifically, The Westbury Viaduct is located east of Brackley and crosses the floodplain of the River Great Ouse. while it is the longest structure of its kind in the Brackley area.
The project was carried on and delivered by EKFB, a joint venture comprising four major construction and engineering companies such as Eiffage, Kier, Ferrovial Construction and BAM Nuttall. It should be noted that these organizations are responsible for delivering a major section of the HS2 route, including bridges, viaducts, earthworks and other essential infrastructure.
In addition, one of the most notable features of Westbury Viaduct is its innovative double-composite design which was developed through experience with high-speed railway bridges in France. Therefore, this approach combines steel girders with reinforced concrete layers above and below the beams, creating an efficient box-beam structure. Furthermore, according to EKFB, the design reduces the quantity of steel and concrete required compared with many conventional alternatives, helping to lower the structure’s embodied carbon.

Constructing the viaduct required careful planning and specialist engineering techniques. A total of 2,695 tons of steel beams were assembled at the northern abutment before being moved into position across the concrete piers between March and October 2024. Special low-friction pads were used to facilitate the movement of the steelwork over temporary bearings during installation.
Once the beams were in place, a travelling formwork system was used to cast the concrete deck in successive 42-metre sections. In addition, prefabricated parapets were then lifted into position and secured, completing the main structural works. Also, the remaining activities include removing temporary construction platforms and restoring the surrounding floodplain.
It should be noted that EKFB is a joint venture established by Eiffage, Kier, Ferrovial Construction and BAM Nuttall, bringing together their expertise in civil engineering, infrastructure delivery and complex construction projects. Moreover, each company contributes to the project with specialist knowledge and resources in order to enable the partnership to undertake large-scale work that requires close coordination between design, construction and engineering teams.
In all, the completion of Westbury Viaduct demonstrates how innovative structural design can improve material efficiency while meeting the technical demands of modern railway infrastructure. It also highlights the importance of collaboration between contractors, designers and specialist supply chain partners in delivering complex structures safely and efficiently.
Sources: newcivilengineer.com, sitelive.group, railtechnologymagazine.com
A new edition of Eurocode 4 has been released, providing updated guidance for designing composite s...
The southern navigation channel bridge of the Hangzhou Bay Cross-Sea Railway Bridge reached a major...
Concrete structures are constructions that utilize concrete as the primary building material. Conc...
The Dutch city of Nijmegen has now the longest concrete 3D-bicycle bridge in the world. The length...
The construction industry has changed significantly over the last decade. Specifically, robotics, ar...
Beam, in structural engineering, is a horizontal structural element that is designed to carry and...
A new milestone has been reached on the Xi'an–Chongqing High-Speed Railway, with the Miaojialiang Br...
Bennerley Viaduct, a Victorian railway bridge which runs between Derbyshire and Nottinghamshire, ha...
The new pedestrian tunnel connecting Grand Central Terminal with the No. 7 subway line at 42nd Stree...