Florida SunRail Phase 1 Almost Completed

Phase 1 of the Central Florida SunRail project is almost finished and service on the route will begin once all 12 stations are completed.  Construction began on the 32-mile route connecting Volusia County to Orlando in January 2012.  The rail line is expected to cost $615 million to construct and $432 million to buy the right of way and tracks.  The federal government, the state of Florida, and the three counties that the rail line passes through are financing SunRail.  The federal government is paying for half of the project through a federal transit “New Starts” grant, and the state of Florida and the counties will each par for 25% of the project.  SunRail was originally approved in July 2007, and it took over four years to plan the route and receive funding.  This period included a six-month freeze on all contracts and a legislative review ordered by Florida Governor Rick Scott.